Inside Baytown's $982 Million Five-Year Building Plan
A project list this large is easier to evaluate when readers know the timeline and category of each planned investment.

Baytown's capital plan for fiscal years 2027 through 2031 lists $982,107,134 in planned projects. Only $111,275,087 of that is new money in the first year, FY2027, which began Oct. 1, 2026. And voters said yes to just $34,700,000 of the $151,346,900 in bonds they were asked about in November 2025.
The Capital Improvement Plan, or CIP, is the city's list of what it intends to build or rebuild. A plan is not money in the bank. This story separates the plan, the yearly allocation and the bond vote, then shows what the approved money is paying for and what the failed propositions would have built.
The short version
- The CIP for FY2027-2031 plans $982,107,134 in investments.
- The Capital Projects Funds get $111,275,087 in new allocations for FY2027.
- In the November 2025 bond election, voters approved 2 of 6 propositions, worth $34,700,000 in all.
- Prop B Mobility, at $30,450,000, covers streets, sidewalks and traffic.
- Baytown's 2040 Comprehensive Plan was adopted by the City Council in May 2022.
The plan and the first year
Over five years, $982,107,134 averages out to about $196 million a year. The new FY2027 allocation of $111,275,087 is about 11% of the five-year total.
For scale, the city's all-funds budget for FY2027 is $424,324,581, a 6.7% increase from FY2026. The $111,275,087 in capital allocations is about 26% of that. Treat the share as a rough scale. The two figures are measured differently, and the capital plan runs across several years. The capital plan covers more than running a city. It covers building it and rebuilding it.
Three words do most of the work in this story: - A plan lists projects the city intends to build over several years. Here the plan covers FY2027 through FY2031, five fiscal years. FY2027 began Oct. 1, 2026 and ends Sept. 30, 2027. The council adopted the FY2027 budget on Sept. 10, 2026. - An allocation is money the budget sets aside for capital projects in a given year. Here it is $111,275,087 for FY2027. - A bond is a vote on borrowing for named projects. In November 2025, voters approved $34,700,000 of the $151,346,900 in requests, about 23%.
Prop B was most of what passed. Its $30,450,000 is about 88% of the $34,700,000 approved. That is why street renewal looms large in the approved list.
What voters approved in November 2025
The city put six bond propositions to voters. Two passed.
Approved: - Prop B, Mobility (neighborhood streets, sidewalks, traffic): $30,450,000. - Prop D, Facilities (Fire Station 4 design and acquisition only): $4,250,000.
Not approved: - Prop A, Thoroughfares: $69,864,400. - Prop C, Drainage: $14,025,500. - Prop E, Wetlands Center education facility and arboretum: $13,000,000. - Prop F, Parks: $19,757,000.
The two approved items total $34,700,000. The four that did not pass add up to $116,646,900. All six together came to $151,346,900.
In May 2026, the council unanimously approved selling the voter-approved bonds, about $34.7 million in general obligation bonds, along with roughly $59.5 million in certificates of obligation for water and sewer upgrades and street and drainage work. Certificates of obligation are a different tool. The council can issue them without a public vote, which is why they did not appear on the ballot.
Inside Prop B
The $30,450,000 for mobility is broken into named projects: - Annual asphalt street renewal: $20,000,000. - Sidewalk and ADA work (sidewalk and pedestrian crossing improvements): $2,500,000. - North Alexander traffic signal relocation: $7,499,000. - Jenkins Park to Goose Creek Trail connection: $451,000.
Those four pieces add up to $30,450,000. So the mobility money is not only paving. A $7,499,000 signal program on North Alexander and a $451,000 trail link between Jenkins Park and the Goose Creek Trail ride along with the asphalt.
Prop D is smaller and narrower. Fire Station 4 is being replaced, and the $4,250,000 covers land acquisition and design. Voters approved design and acquisition, not construction. The city pages do not say what will pay for construction.
What the failed propositions would have built
The city's bond page lists the projects behind each proposition that did not pass: - Prop A, Thoroughfares: Garth Road reconstruction, Phases C, D and E ($35,858,000); Cedar Bayou Lynchburg widening, Phases 1 and 2 ($27,053,000); and West Lobit Avenue ($6,953,000). - Prop C, Drainage: West Baytown drainage improvements, Phases 2 and 3 ($10,525,500); Rollingbrook drainage from Garth Road to Main Street, design only ($2,000,000); and West Main drainage, design and acquisition only ($1,500,000). - Prop E, Wetlands Center: Phase 1 of an education facility and arboretum gardens ($13,000,000). - Prop F, Parks: Wayne Gray Sports Complex ($5,450,000); Unidad Park improvements ($9,307,000); and Gene and Loretta Russell Park, about $5,000,000, a match with the county and an estate.
Those projects are not funded by that vote. Drainage and parks lost, and drainage is the one most Baytown neighbors feel the next time it rains hard. A project that fails at the ballot can still come back as a smaller ask, get paid for another way, or sit on the list. The city's pages do not say which. The city's advisory committee chair called the partial result a win and stressed better planning and a new panel to oversee the approved projects.
The plan is not the bond
The $982,107,134 plan and the $34,700,000 in approved bonds are different numbers. Bonds are one way to pay for projects. Cash from the budget, certificates of obligation, grants and utility revenue are others. That is why a project can sit in the five-year plan without a voter-approved dollar behind it.
The plan is also not adopted once and left alone. Each year brings another budget, and the list moves with it.
Long-range planning behind the list
The Baytown 2040 Comprehensive Plan, adopted in May 2022, sits behind the capital list. The city's long-range plans page also links the 2013 Mobility Plan, and says current future land use and zoning maps are in the city's GIS map. The city adopted a new Unified Land Development Code in 2025.
What to check
- Check whether a project is planned, funded, under contract or complete, and which fiscal year the number comes from.
- A multiyear project total is not the same thing as the amount that will be spent in one year.
What this means for you
Start with the FY2027 adopted budget on the city's website. The capital plan is in it, project by project. Find the streets, drainage and parks near you, then ask whether each one has voter-approved or budgeted money behind it. Streets are the clearest case: $20,000,000 of the approved Prop B is for annual asphalt street renewal. City council meetings are open to the public, and the agenda lists capital items before the vote. If a drainage ditch or a park missed the cut, council is where a resident can say so.
Sources
- City of Baytown: FY2027 Adopted Budget (https://baytown.org/Archive.aspx?ADID=1317)
- City of Baytown: 2025 Bond Projects (https://www.baytown.org/1447/2025-Bond-Projects)
- City of Baytown: Long-Range Plans and Studies (https://www.baytown.org/551/Long-Range-Plans-and-Studies)
- City of Baytown: Planning and Zoning (https://baytown.org/191/Planning-and-Zoning)
- The Baytown Sun: Council greenlights voter-approved bonds for streets, water lines, fire station (https://baytownsun.com/news/council-greenlights-voter-approved-bonds-for-streets-water-lines-fire-station/article_1e4d2013-d1fa-4fac-8274-1e11b0f964e9.html)
- The Baytown Sun: Baytown City Council reflects on partial bond success (https://baytownsun.com/news/baytown-city-council-reflects-on-partial-bond-success/article_8dc10c84-1ddf-4aa3-83d9-0d44c3b273dc.html)